Month 2004-12 December
Meeting of 2004-12-6 SPECIAL MEETING
MINUTES
LAWTON CITY COUNCIL SPECIAL MEETING
DECEMBER 6, 2004 - 6:00 P.M.
WAYNE GILLEY CITY HALL COUNCIL CHAMBER
Mayor John P. Purcell, Jr. Also Present:
Presiding Larry
Mitchell, City Manager
John
Vincent, City Attorney
Kathy
Fanning, City Clerk
Mayor Purcell called the meeting to order at 6:10 p.m. Notice of meeting and agenda
were posted
on the City Hall notice board as required by law.
ROLL CALL
PRESENT: Bill
Shoemate, Ward One
Rex Givens, Ward Two
Glenn
Devine, Ward Three
Robert
Shanklin, Ward Five
Stanley Haywood, Ward Seven
Randy Warren, Ward Eight
ABSENT: Amy Ewing-Holmstrom, Ward Four
Jeffrey Patton, Ward Six
BUSINESS ITEMS:
1. Consider discussing construction alternatives for transferring
water from Lake Waurika and
Lake Ellsworth and authorizing staff to prepare plans and specifications for the preferred
alternative. Exhibits: Memo from Public Works Director dated November 17, 2004.
Jerry Ihler, Public Works Director, presented an Engineering report giving several alternatives
for transferring water within the existing system from Lake Waurika to Lake Ellsworth to Lake
Lawtonka. The report evaluates the cost benefits and the additional duration that could be added
during a prolonged drought period to be able to continue to provide a water supply to the
citizens.
Ihler stated the operation of Lake Lawtonka is by gravity flow to the Medicine Park
treatment
plant. When the lake elevation gets down to 1,341, or approximately 4.5 feet down from the top
of the gate, pumps are activated at Lake Ellsworth sending water through a 12 mile, 42 pipeline
to Lawtonka. The pumping policy provides that when Lake Ellsworth gets down ten feet from the
top of its gate, pumps are activated at Lake Waurika sending water through a 42 pipeline to the
Lawton relift station, and then to the east side of the dam at Lake Ellsworth. The first use is from
Lake Lawtonka, then Lake Ellsworth, then Lake Waurika.
Ihler said Lake Lawtonka is the primary water supply for the Medicine Park treatment
plant. The
normal pool operating level elevation is based on the Oklahoma Water Resources Board dam
safety requirements to be able to pass a 500-year maximum probable flood. To do that through
our dam and when those storms occur, we must have the operating pool levels at those elevations
shown in Table One, 2.2 feet down at Lawtonka and 2.5 feet down at Ellsworth. Lake Lawtonka
contains 37,000 acre feet; Lake Ellsworth contains almost twice as much as Lake Lawtonka, and
Lake Waurika has about five times that of Lawtonka, but the City receives only 60% of that so
our actual usage is 110,000 acre feet at Waurika.
Ihler presented Table Two showing the present water supply and durations. If drought
conditions
exist and no additional runoff is received, the water supply would run out at Lake Lawtonka after
a 14-month period. With the ability to pump from Lake Ellsworth, it increases that duration from
14 months to 27 months, and with the ability to pump from Lake Waurika, it increases that
duration for a period of 43 months. Ihler presented Table Three showing existing conditions
and
explaining how improvements would increase available water supply depending on water supply
levels and drought factors.
Ihler stated the weak link in the system is at Lake Ellsworth when the water elevation
gets down
to 1213 and the pumps can no longer be used to transfer water to Lake Lawtonka. Attempting to
pump after that level is reached would cause damage and cavitation to the pumps. Ihler said there
is a similar problem at the water treatment plant; at elevation 1320, which is about 25 feet down
from the top of the gates, water can no longer gravity flow from Lake Lawtonka into the
Medicine Park water treatment plant and provide enough head to be able to push it through the
water treatment plant with a gravity system, so there would be serious trouble in that water could
not be treated and sent to town.
Ihler provided and discussed five alternatives, with one being to do nothing
which would not
have any associated cost but would also not correct the problems.
Alternative 1A: The 42 raw water line from Lake Waurika enters Lake Ellsworth
on the east
side of the spillway. The Fort Sill National Cemetery will connect to the Waurika pipeline
downstream of the surge tank 900 feet south of the spillway. This alternative would construct a
new 36 line connecting the proposed 36 line to be installed by the cemetery. Once inside
the
pump station, the new pipeline would transition above grade and connect to the existing 36 line
leading from the intake structure at the pump header, connecting directly to the existing pumps.
Estimated cost is $391,000.
Alternative 1B: Construct a new 36 line connecting the proposed 36
line to be installed by the
cemetery. Once inside the pump station, the piping would transition above grade and continue
through the pump station and down the corridor leading to the intake structure, parallel to the
existing 36 pipe. The ultimate connection to the intake structure would be through a 36
wall
sleeve installed with the original construction. Estimated cost is $513,000. There was a little
concern about the velocities coming through the pipe, it was an engineering function to look at it
and we added a second pipe to be able to reduce the velocities where one pipe takes water to
Lake Lawtonka and then the other pipe would gravity flow to the Southeast Water Treatment
Plant. The benefits are not that different so this alternative is not recommended.
Alternative 2: Provide two low-lift/high volume booster pumps attached to the
intake structure.
Cost estimate is $281,000. The advantage is the lower cost but a major disadvantage is that when
we get around 1200, we will no longer be able to pull out of the lake and we are back to the same
situation we are in, we just have about 13 more feet that we could pump, but if we have a really
severe drought, we still could not use the Waurika water if we get below that level.
Alternative 3: Provide a new 36 line from the Lake Ellsworth outlet structure
and proceed
along the face of the dam spillway to the intake structure. 40 diameter holes would need
to be
drilled through the outlet and intake structure walls and most of the construction would have to
occur at or below the water surface elevation. Estimated cost is $489,000. Major disadvantage is
the cost associated with extensive construction, most of which would take place under water.
This would also create problems in future inspections and debris could damage the line when the
gates are operated. This alternative is not recommended.
Ihler summarized the alternatives shown.
Shanklin asked if the 42 line comes in at a sluice gate. Ihler said no, this slide
is on the west side
where the pump station is located but it is the same configuration on the east side on the bottom
except you do not have these draws at an upper level so we will have to modify the east side for
part of the Southeast Plant to be able to pull out at different levels of the lake and improve the
quality, and that cost is shown as $100,000. Ihler said that must be done even if the do
nothing
alternative is chosen.
Ihler said Alternative 1 is at a lower cost but long-term maintenance and operation
costs would
be higher due to the need for a diesel-powered generator. He recommended Alternative 1A as
the most cost effective measure, when construction, maintenance and operational costs are
considered.
Shanklin said years ago we went to Waurika and they made the statement they could pump
the
water all the way to Mount Scott, which was not true evidently. He asked if we have to use the
relift pump station to take it on to Lake Ellsworth. Ihler said yes. Shanklin said those three pumps
alone could not get it there. Ihler said we cannot pump from Lake Waurika to Lake Ellsworth
without using the relift pump station.
Ihler said eight inches of rain were received during November, causing Lake Ellsworth
to rise
about five feet. Drought conditions have existed for the prior three years; the lowest point at
Ellsworth was on October 6, 2004, where it was down 15.55 feet, but is now up 18.4 feet, so
October and November have been very generous to Lake Ellsworth in runoff. The lowest point at
Lake Lawtonka occurred a year ago today and that was 1338.4 so in the last year it has risen 4.6
feet.
Ihler explained previous CIP expenditures, project deferments and savings. Recommended
funding source is the 2000 CIP. He said $4 million in water line projects had been deferred and
may be able to be reinstated if revenues and interest are good. Design will not be completed until
March and at that time the amount of funding available will be known.
Warren asked if the choice would still be 1A if it were not for the funding difference.
Ihler said
yes.
MOVED by Warren, SECOND by Shanklin, to direct staff to move forward and prepare plans
and specifications for Alternative 1A. AYE: Givens, Devine, Shanklin, Haywood, Warren,
Shoemate. NAY: None. MOTION CARRIED.
There being no additional business to consider, the meeting adjourned at 6:40 p.m. upon
motion,
second and roll call vote.