Month 1999-4 April
Meeting of 1999-4-6 Special Meeting
MINUTES
SPECIAL CALLED MEETING
LAWTON CITY COUNCIL
APRIL 6, 1999 - 5:30 P.M.
WAYNE GILLEY CITY HALL COUNCIL CHAMBER
Mayor Cecil E. Powell, Also Present:
Presiding Bill Baker, City Manager
John Vincent, City Attorney
Brenda Smith, City Clerk
Lt. Col. Jeff Ewing, Fort Sill
Liaison
The meeting was called to order at 5:30 p.m. by Mayor Powell. Notice of meeting and
agenda were posted on the City Hall notice board as required by State Law.
ROLL CALL
PRESENT: G. Wayne Smith, Ward One
Richard Williams, Ward Two
Jeff Sadler, Ward Three
John Purcell, Ward Four
Robert Shanklin, Ward Five
Charles Beller, Ward Six
Stanley Haywood, Ward Seven
Randy Warren, Ward Eight
ABSENT: None.
Baker introduced Gary Jackson, Assistant City Manager, and he was welcomed to the
City.
BUSINESS ITEM:
1. Receive a presentation from the Corps of Engineers on the Meadowbrook Creek
Local Flood Protection Project and select an alternative for completion of the study.
Exhibits: Location Map.
Jerry Ihler, Public Works/Engineering Director, said the City has been in a joint venture
with the Corps of Engineers in a feasibility study which began September 1997, with
anticipated completion in the spring of 1999. A decision is needed on which of these five
alternatives to pursue. He introduced Gene Lilly, Project Manager, from the Corps of
Engineers.
Lilly said detention structures and channel improvements have been evaluated; one
alternative is to take no action and four other alternatives are provided regarding
channel improvements. A matrix was developed and had been provided to Council
showing alternatives and comparisons to allow for a decision to be made that would be
best for the community and allow the Corps to submit that plan for approval.
Lilly said the feasibility study cost share agreement was approved in August 1997; the
study team identified potential solutions for the flooding problems and presentations
were made to the public in April and in August 1998. Following the August meeting,
there was a need to identify additional alternatives because of public concerns regarding
the removal of trees. Two additional alternatives were identified, those being Plans 8
and 9 in the matrix. There is a need for selection of the best alternative that meets the
needs of the community at this point. The Corps would then complete the feasibility
study, request approval of that feasibility study, and subject to that approval, initiate
plans and specifications, and subject to further approval, execute a project cooperation
agreement, acquire real estate and construct the project.
Preliminary proposed schedule to complete the activities is proposed for the feasibility
study to be completed by February 2000; then initiate plans and specifications in March
2000; submit plans and specifications for approval and request construction approval to
initiate the project cooperation agreement in December 2000; after execution of the
project cooperation agreement, there is a year scheduled for real estate acquisition,
followed by approximately four months for the competitive bid contracting process,
which would put construction beginning in April 2002.
Lilly said from the Corps of Engineers perspective, the plans presented on the matrix all
meet the benefit cost criteria and they are prepared to take the plan the City prefers and
forward it with a request for approval. He said he could not guarantee that it would be
approved, but that would be his intent, and following that approval, the Corps would
initiate plans and specifications, followed by execution of the project cooperation
agreement, real estate acquisition and then construction.
Baker asked what constitutes the delay between the time plans and specifications are
prepared until construction could begin in April 2002. Lilly said plans and specifications
take approximately nine months, and one month is scheduled to execute a project
cooperation agreement after the completion of plans and specifications, and a year is
scheduled for real estate acquisition, and the competitive bidding process takes four
months.
Purcell asked if all five of the plans assume that the B-1 reservoir is operational. Lilly
said yes. Purcell asked if any of the dollar figures shown on the matrix include costs for
the B-1 reservoir. Lilly said the dollar figures are for the channel improvements, not for
B-1.
Beller asked if $3 million had been set aside and if that included the cost of the B-1
reservoir and if that was included in these costs. Lilly said it is not included in the costs
on the matrix. Beller asked if there was a cost estimate on the B-1 reservoir. Ihler said
when the $3 million was earmarked, $1.5 million was earmarked for the joint project with
the Corps and $1.5 million for the B-1 reservoir. Ihler said he anticipated the cost for the
B-1 reservoir to be $1.7 to $1.8 million. Beller said there may be a shortage and Ihler
said, depending on the alternative selected, there could be a shortage in both.
Jim Leach, hydraulic engineer with the Corps of Engineers on this study, said he
developed the information that determines the amount of flow and the flood depths. He
presented a slide showing the drainage area for the Meadowbrook Creek addition, and
pointed out various reference points. Photo images and contour data was provided by
the City in many instances. Existing 100 year flood plain for Meadowbrook Creek was
pointed out on a slide, as well as the homes that are subject to the 100 year flood; four
homes were incorrectly identified as they are on a small hill. 57 homes are in the
existing 100 year flood plain and 52 are in the 10 year flood plain. The existing
conditions represent the first alternative of taking no action.
Leach said Plan Four is a grass lined channel starting near the golf course, proceeding
up through Meadowbrook Creek to a small antique store. It has a 55 foot bottom width,
trapezoidal shaped channel that is grass lined with a small concrete section in the
middle that would be approximately seven foot wide or ten foot wide to allow for
maintenance vehicles. Replacement of the Meadowbrook Drive bridge and the 51st
Street bridge would be required to accommodate the new channel width. Eight homes
would have to be purchased and removed to allow for construction of the channel. He
presented a slide showing how this plan would affect the flood plain, and five homes
would still be in the 100 year flood plain; three would remain in the 10 year flood plain
just south of the Meadowbrook Drive bridge. Plan Four would provide a small amount of
flood reduction at a certain point, but as it moved upstream, the channel modification
would take hold and by the time it gets to Meadowbrook, there is a large amount of flood
reduction. There would be approximately 3-1/2 feet of flood reduction at the
Meadowbrook Drive bridge and about 5-1/2 feet of flood reduction at the 51st Street
bridge.
Leach said Plan Six is the first plan they investigated. It consists of a grass lined
channel with a 65 foot bottom width in certain areas and a 55 foot bottom width for the
remainder. It begins at the mouth and goes all the way through at Cache Road. With
this plan, the same eight homes would have to be purchased and relocated. The
Meadowbrook Drive bridge and 51st Street bridge would be replaced. There would be a
three to one vertical side slope on the channel and the top width varies between 90-120
feet wide. He said the cross sections remain the same for the plans. Leach said the
existing 100 year flood plain would be contained within the channel, as well as the 10
year flood plain. A slide showed the existing conditions for 100 year and 10 year flood
plains, and the result of the proposed improvements. Plan Six would have no homes
remaining in either the 100 year or 10 year flood plain. The 100 year flood would be
reduced by 5-1/2 feet at Meadowbrook Drive, and at 51st Street it would be reduced by
6-1/2 feet in depth.
Leach said Plan Eight is very similar to Plan Four, except no channel work would be
conducted between Meadowbrook Drive and a little east of 51st Street. The
Meadowbrook Drive bridge would not be replaced, but the 51st Street bridge would be
replaced. 45 homes would remain in the 100 year flood plain with Plan Eight, and five
homes would remain in the 10 year flood plain. Channel work would begin to the north,
no work would be done for a certain distance, and channel modification would resume at
51st Street. There will be three feet of flood reduction on the downstream side of
Meadowbrook Drive for the 100 year flood, and about 2-1/2 feet of flood reduction in
another vicinity.
Leach said Plan Nine is the same as Plan Eight except nothing would be done on the
downstream portion, and the only channel improvement would be from the 51st Street
bridge to the antique store. The 51st Street bridge would be replaced and the same
eight homes would have to be purchased and removed. Reduction in flood plains were
shown on a slide. 51 homes would remain in the 100 year flood plain and 42 homes
would remain in the 10 year flood plain. There would be no reduction in flooding in a
certain area, upstream at 51st Street there would be a 1.3 feet reduction in the 100 year
flood.
Leach presented a slide to show how the various channel plans compare with the
existing conditions.
Shanklin asked if the Corps studied the area at 44th and Gore and to the south. Leach
said no, they took the existing flood plain conditions for Wolf Creek where the east,
middle and west branches come together, although they do have the existing conditions
for Gore. Shanklin said he had felt for a great number of years that the area caused
problems. He said 44th and Gore had 100 feet of bridge 12 foot deep, 1,200 foot boxes,
and if water is running five foot deep you have 500 square feet of water going south
down stream. It goes onto State land and there is an ox bow, trees, and a fence under
the trestle, although it may have been removed, but when it gets to 38th and Lee, it may
be a 100 foot bridge but at five foot, the way it is sloped, only 275 feet of water can get
through there. He said he could not believe that those conditions did not cause water to
backup further up stream.
Leach said that is a commonly asked question because most people think the slope of
the stream may be flat enough that it would cause a back water effect. He said the slope
of Meadowbrook Creek is sufficiently steep enough in terms of hydraulic capacity that
the effects from the main stem of Wolf Creek play out about mid-way through the golf
course, so there is sufficient slope on Meadowbrook Creek that Meadowbrook Creek
itself takes control with the high elevations. Shanklin asked if there is enough elevation
fall that will not affect it. Leach said yes, for the 100 year flood; there could be problems
with a 500 year flood, but there is quite a bit of drop as it flows through the golf course.
Shanklin asked if the figures showed 20 foot of fall or 20 foot of water. Leach said there
is ten foot of fall from where the channel work would begin down to where Meadowbrook
Creek dumps into the main stem of Wolf Creek. Leach said if they were to build the full
channel from where Meadowbrook Creek runs into the main branch, because of the
significant drop as it gets close to the main branch, they would have to build a drop
structure to keep from having erosive conditions at the end; there is a lot of fall based on
the contour information. Shanklin said it shows almost ten feet of fall in a 1,000 feet area
and asked if that was correct. Leach said about 7-1/2 feet, yes, and 9 feet of fall in
2,000 feet.
Mayor Powell said this was not advertised as a public hearing and asked that Council
agree to receive comment due to the large attendance at the meeting. Council agreed.
Earl Barton, 810 NW 50th Street, said he had lived there for 30 years and when
Meadowbrook Creek was flooding, he would walk there through his back gate and down
the sidewalk adjacent to the creek to see how bad the flood was, and much of it is
coming from 53rd, 49th, 48th and through that area into a small channel. He said if he
could walk adjacent to the creek to see the flooding, it would show that the flooding was
from more than just the creek. Barton said he would like to know what the alternatives
would do for that problem.
Leach said the plan does not address local drainage problems, such as if there is a
street that is carrying a lot of water and people have difficulty in that regard, this plan
does not specifically address those problems. There will be inlets into the channel at
various locations for water that is coming in from the sides to properly get within the
channel, but there will still be flood problems in low areas and on some streets that this
project will not fix. The main purpose of this project is to carry the flood waters that are
coming primarily from the large, upstream area of the drainage basin down through
Meadowbrook Creek. There will still be some local drainage problems that the project
will not address, although they would provide access for the water as best they could off
of the little side areas, but it will not solve everything.
Kay Terrill, 811 NW 51st Street, said she had lived at that address for 32 years. She
asked when was the last time barriers were used to block off Meadowbrook Drive and
that she and her husband had observed that the water seemed to be flowing better,
possibly because it had been cleaned out. Terrill said the barriers had been up two or
three times a year in the past, but it may have been a year since they had been put up
recently.
Terrill asked Leach to put up the slide showing Plan Four. She asked where the water
coming down the channel goes when it gets to a certain point and said it would come
swooshing down the channel. She said it does not go anywhere but the country club
and they had never understood where the water was going and that the slide did not tell
them either.
Terrill asked Leach to put up the slide showing Plan Eight and asked if he said there
would be no flood reduction between Meadowbrook and 51st Street. Leach said there
would be some reduction but there would be no channel construction in that area. Terrill
said if Plan Eight were to be adopted, that would be acceptable because there is no
flooding there anyway, and that the house Sadler currently lives in got water in it 20
years ago and that was the only time she knew of any house in that area getting water.
Terrill said the phrase channel modification indicated clearing out what is there now,
which is beautiful, and replacing it with a ditch; she said channel modification reminded
her of the phrase ethnic cleansing and that the phrase is completely deficient in
indicating the damage that occurs and would occur in destroying their environment. She
said we should call it what it is, and that is digging a ditch and destroying the
environment.
Al Terrill, 811 NW 51st Street, asked in Plan Eight what would happen in the park area
on 51st Street and if there would be a holding pond. Leach said at the lower end on Plan
Eight, the modified channel will transition back to the natural channel, which is much
narrower. He said bank protection, such as stone or rip rap, will be needed to prevent
erosion; flood water will be squeezed down in Plan eight as shown for the 100 year flood
plain when it gets to the lower end and the golf course; the modified channel will
transition back into the natural channel.
Terrill said the plans call for purchase of homes and asked at whose expense that would
be done. Lilly said land acquisition and utility relocation are parts of project
implementation cost, which is shared by the Corps and the local sponsor, which would
pay either 35% or 50% depending on the cost of the project, and in this case, Lawtons
share would be 50%. Terrill asked how much had been identified for purchase of homes
and the bridge replacement costs. Lilly said the lands and utility relocation preliminary
estimates, depending on which plan is selected, would range between $1.6 and $3.3
million. Terrill asked if the Corps would participate in the cost of the bridge on 51st
Street and response was that the costs would be shared and the bridge estimate was
$350,000 to $500,000.
Sadler said some plans show Lawton and the Corps paying $1.4 million each and asked
if that included the purchase of the homes. Lilly said Lawtons share is 50% and a large
part of this is the land and buildings.
Ted Lechner, 808 NW 50th Street, asked for the slide showing the aerial view of the
area and asked if any of the plans went even mid-way into the golf course. Leach said
Plan Six is from the mouth up to Cache Road; Plans Four and Eight start and then end
at an antique store; Plan Six goes all the way through the golf course and it would
contain all of the 100 year flood and straighten the channel and reduce flood depths
more for the lower section, but provide no benefit for the area upstream. Lechner said
the computer model shows that houses along Meadowbrook, such as Mr. Underwoods
house, would not flood in the 100 year flood. Leach said that was correct, the east side
of the creek and south of Meadowbrook would not flood in a 100 year flood but five
homes would still be in the flood plain.
Lechner asked if Plan Six was much more expensive. Leach said it is more expensive
due in part to the greens and tee boxes through the golf course. Lechner said the model
did not account for collateral drainage coming in from the side streets and asked if the
plan would accommodate that water. Leach said he took into account the total amount
of water that would be running off of this total area but did not count the amount of water
coming in from each little street. Lechner asked if there could be so much side drainage
that the program conclusions are thrown into doubt. Leach said no, the amount of flow
coming in from the drainage area north of Cache Road is much more than would be
contributed by this one area south of Cache Road. Lechner suggested that purchase of
the houses alone might be sufficient.
Purcell said the information shows that under Plan Six no homes would remain in the 10
year or 100 year flood plain and asked if those who own the homes now who are
required or have the option to buy flood insurance would be relieved of that
responsibility if they were outside the flood plain. Ihler said yes. Beller asked if that
would still be a flood plain area. Ihler said the 100 year flood plain would be carried
within the channel and a Letter of Map Revision would be required for submission to
FEMA to update the maps to show the current conditions resulting from the
improvements.
Mary Burrell, 5114 NW Liberty, expressed concern about the water on the smaller side
streets and asked why assistance could not be provided to relieve that situation. Leach
said this project is to modify the main channel itself for the drainage basin, and some
relief may be provided for local streets due to the inlets that will be provided into the
channel but that it would not completely solve that problem. Leach said the bridge at
51st Street would be replaced with a wider and taller structure. Mayor Powell said Plans
Four and Six call for replacement of both bridges, and Plans Eight and Nine call for
replacement of only the bridge on 51st Street.
Bill Malone, 4632 Meadowbrook, said he had lived at that address for 33 years and
served as the President of the Lawton Flood Association of Meadowbrook. He said
Flood stands for Frequent Loss Of Our Domain. He said he had lived in the area
since 1966 when there were three to five houses there. Malone said the City Engineers
had told him it was against the ordinance to defer water over more than three neighbors
houses, and they had no problem with flooding until Memorial Day weekend in 1979, so
someone is not detaining water as the City Code says. He said the Flood Members
would like to see Plan Six from the mouth of the Meadowbrook Creek to Cache Road,
the full channel. No homes would be in the 10 or 100 year flood plain for the money
spent.
Malone said he and his wife put their house up for sale in July 1998. A reputable
appraiser established the price at $250,000 for the 3,500 square feet home, and they
asked $245,000 because they knew it was in a flood area. Generals, Colonels, and
several business people looked at it and were very interested until they found out about
the flooding problems. The price has been reduced to $190,000 and no one has made
an offer so it is obvious what this situation does to the property values in the area. He
asked how many houses, businesses, car lots, and apartments have been built west of
46th Street since 1966 with water now running into this small creek. Malone said the
Flood Association requested the Council, as the elected officials, to vote for Plan Six
and to vote from the heart, and not because of politics. He said 60-70% of the neighbors
in the area were on fixed incomes and flood insurance costs from $400 to $600 a year;
the Flood Association recommends Plan Six as the best plan for the dollar spent, and if
not, they would like to ask for Plan Four which would leave only five homes in the 100
year flood plain.
Malone said the Flood Association understands that most of the CIP money had been
set aside for this project, and the CIP election is coming up in 1999. He said all he had
heard from City officials was that the residents should have known better than to have
bought in that area. The City and Corps of Engineers have spent a lot of time and
money to solve the Citys problems in this area. He said Lawton has made progress and
is a nice place and that he and his wife had been in business here for 43 years and plan
to retire here. Malone asked that the CIP money be put to work and used for what it was
voted in for, and that the flooding has been going on for 20 years. He asked what the
elected officials planned to do for Meadowbrook Addition.
Burl Boyce, 4630 NW Meadowbrook, said everyone is asking where the water goes
when it gets below Meadowbrook bridge and that the answer to that question is that it
goes in the back of his house. He said the reason for that is when the creek fills up
completely, there is no place for the water to get out of the area because it hangs up
and then backs up. Boyce said if you build a creek or channel that will do the job, it will
stop the problems, plus you will be able to have more development and help everyone in
the City be able to make money, taxes and help the City grow.
Rick Herbert, 1110 NW 51st Street, said Malone mentioned what would be the best plan
for the dollars spent, and that is Plan Six where the water would go all the way through
to the new channel. He said the area south of the Meadowbrook bridge had already
been widened, and rip rap is in place along the bank, and that he did not know if that
would continue north to Cache Road. Herbert said every tree that is taken out would be
replaced according to the information provided, and that trees would be on the slopes,
although the trees would not be 300 years old. He said this is not a giant concrete ditch,
and it would look pretty good and be similar to those in Oklahoma City and Wichita
Falls. Herbert said most people have fences and they are not looking right into the
creek.
Herbert said Plan Four is a partial option and would cost $2.1 million. He said the bars
and graphs were fine but that most people would not understand seeing a red bar run
across a blue bar, but the bottom line in Plan Four is that you would spend $2.1 million
and that included everything that would be done, and you would only have five homes
that would remain in the 100 year flood plain. Herbert said you can forget the 10 year or
100 year flood plain or 11 inches of rain per year, because there is a flood if three
inches of rain is received in 30 minutes. He said the problem is so much water coming
into this area at one time. Herbert said those living on Liberty Street have told him that
when the creek gets up, their water backs up. He said he felt if the creek were widened,
the water would not build up and the street drainage would flow into it.
Herbert said if you go from Plan Four to Plan Six, it is $900,000 but you are talking
about 57 homes that are paying flood insurance. Herbert said Plan Six shows that no
homes would remain in the 100 year flood plain and the water would be in the ditch. He
said Lawton is growing all the time and restaurants do not come to a town that is dying,
and they are coming in all over the place and Fort Sill is not getting smaller. Herbert said
if no improvements are made on the middle section of the channel, the water could get
higher near those houses. He said if this is going to be done, it should be done right.
Herbert said the residents inherited the sewer problem and that this flooding problem
should be solved because the City is growing and more houses will be built to the west
and the area near Rogers Lane will be developed and more water would be running off.
Herbert said the City should be commended for going ahead with this because he knew
there were people who did not want anything done. He said the money is earmarked to
fix the problem and Lawton could pay $3 million to get a $6 million project, and 57
people would not be paying flood insurance, and that he personally pays $700 a year
and it is based on the size of your home. Herbert said it should be done all the way and
finished and not just do it half way and get the most you can for your money.
Shanklin said he would like to clarify that the Council identified the funds and that it was
not shown on the ballot for the 1995 CIP as an individual project to the voters. He said
Council was trying to help solve this problem but the $3 million that may be spent was
not shown on the ballot and it was set aside as a possibility. Shanklin said it was in error
to say the City was not spending the money as it said it would do. He said there may
have been more projects in the past than there was funding available to do, but that he
wanted to clarify that point.
Johnny Wilson, 7218 Dogwood, said he was the head golf professional at the Lawton
Country Club. He said when the water goes down, it goes all over the country club
property and debris could be found after a hard rain. He said Plan Four would appear to
be dumping more water on the country club. Wilson said Plan Four includes funding for
two greens, Plan Six includes four greens to include tee boxes and bridges. He said
they take a lot of the water that comes through.
Williams asked Wilson the preference of the country club in regard to this problem.
Wilson said they want to be put back like they are, and when this started, they were
closed down to fix some greens and wanted to do something then but that was two
years ago. Williams asked if the country club would be receptive to one of the plans
shown on the list. Wilson said the board of directors would have to answer that.
Shanklin asked if the water from 82nd Street may be as much of a problem as the water
coming from Meadowbrook. Wilson said the aerial shows the lay out and that you can
tell the next day at the golf course that the water came through by the debris that is left
there, and the water comes out of the creek and crosses the golf course.
Shanklin asked if we had ever modeled the detention reservoir that was going to built on
Fort Sill. Leach said Tulsa modeled both B-1 and B-2, as well as an alternative showing
a detention pond on Fort Sill but since it is such a large, uncontrolled area, adding two
more ponds does not do much, dollar for dollar, in this area and you would not notice
much flood protection from it.
Beller said a footnote says that Plan Eight was generally accepted by those attending a
workshop and asked if this was the same alternative that was presented to that group.
Lilly said yes.
Purcell asked the City Attorney if the City could assess part of the cost to the people that
are benefiting from this. Vincent said for streets, sewer lines and water lines, the City
can create improvements districts but would have to research whether that included
drainage. Purcell said they seemed to be talking about everyone wanting Plan Six. The
Mayor asked for order. Purcell said for whatever plan is desired, and obviously Plan Six
was not widely acceptable, but funds are needed for any of the plans and for B-1
reservoir. Purcell said Plan Six shows no homes in the flood plain so there would be no
requirement for them to pay flood insurance, so there would be a savings there and
asked if there could be an adjustment where the residents would be no worse off than
they are now but the flooding would not be a problem.
Shanklin said if he lived there, he would want to maintain that insurance because there
could still be a possibility of a 200 year flood, and because this is all shown on models
and had not been constructed or tested.
Anthony Cominos, 812 NW 50th Street, said he had lived in Meadowbrook since 1966
and had never been flooded. He said he was late in arriving and knew nothing about any
of the plans but that he objected to all of them on the basis that he had lived in
Meadowbrook all of these years. Cominos said he did not care what the Council voted
on because they would do whatever they wanted to do anyway and that was the way it
had always worked and he was not trying to offend anyone. He said regardless of which
plan was approved, he would continue to carry flood insurance and that he paid over
$800 per year for it because there might be one time that he could be flooded. Cominos
said there had been quite a few thunderstorms and rain events in the past few months
and would like to know when the last flooding was, and some cleaning had been done in
the area, and asked when the last time was that anyone had been flooded in that area.
He said he had heard of none and had seen a dramatic change in the flow of the creek
since the mouth had been opened a little bit down stream. Cominos said he would like to
see a plan to work on the country club first since that seems to be the biggest
bottleneck. He asked how many inches of rain there had been since the last flooding
and the result, and said there had been some progress. Cominos said he did not want to
see a ditch behind his house or replace 300 year old trees with one year saplings.
Sheila Pedigo, 1109 NW 52nd Street, said that many comments had been made tonight
to confuse the issue and what it comes down to is homes versus trees. She asked
Council to look at the repetitive flooding in Meadowbrook and to initiate a positive action
to benefit those who are adversely affected by the flooding, a potential killer. Pedigo
said all of the streets in Meadowbrook flood much too often; when homes flood, the
families are exposed to electrical hazards, the possibility of a gas explosion,
contamination of sewage and the threat of snake bites. She said few people realize the
force of storm water when it leaves the banks of a small, meandering creek known as
the middle branch, and affects properties, homes and streets. The risk of drowning is
also a major concern. Pedigo said in the event of a medical emergency, they would be
denied access because there is no way an emergency vehicle can get to their homes
when they flood, and this service should never be denied to anyone.
Pedigo said she was told in 1995 by FEMA in Washington, D.C. and also by the State
Attorney General that it is the responsibility of the local government to handle the
mitigation of storm water in the community. She said flooding brings misery and
hardship and carries a financial burden. Pedigo asked that either Plan Four or Six be
approved, and nothing less. She said the houses that are flooding are their homes and
investments.
Mayor Powell called for a conclusion to public comment and thanked those who
participated.
Williams asked staff how much longer it would be before the B-1 detention pond could
be in operation. Ihler said Triad Engineering is finishing the final design and he hoped
that construction could begin late this summer or early fall. Williams asked a time frame
for construction and Ihler said possibly a 180 day construction contract.
Purcell said he needed an explanation of what the residents of the area would like to
see done.
Warren said all of the plans, except the one for no action, call for the removal of
between 155 and 400 trees. He said he would not let trees stand between people having
a home that flooded and having a home that did not flood. Warren said trees meant
nothing to him in that equation, and trees would be lost in any of the plans although new
trees would be provided, which would not satisfy everyone, but that Council should
accept that fact.
Sadler said he thought a pretty good consensus had been reached at the meeting at the
Library in January, and that a petition had been submitted by many citizens supporting
Plan Eight in writing. He said the no action alternative should not be selected after
everything that has been done. Sadler said Plan Nine calls for no reduction in flooding at
Meadowbrook bridge, which is not acceptable, and that leaves Plans Four, Six or Eight.
He said there is a difference in cost and in trees, the trees being saved are between the
bridges in an area that does not typically flood now and those are the ones he would like
to try to protect. Sadler said eight homes would be removed and the trees next to them
may be removed also, but if no one is living there, then people are not as concerned
about those trees. He said he was stunned to hear people from Flood talking about
Plans Four and Six after all of the discussions that were previously held. Sadler said he
had represented Ward 3 for two years and had never been invited to a Flood meeting,
but when you talk to them personally, they are not in favor of removing 150 year old
trees either.
Sadler said $3 million was earmarked, but $1.5 million of that will be spent on the B-1
detention pond, and that leaves about enough money to do Plan Eight for the $1.7
million required. He said he would like to leave out work on the middle section of the
channel, do the work to the north and south of the two bridges and then do a serious
clean up, which can be done through the $1 on the utility bill that is used for drainage
work. Sadler said Plan Eight seemed to be coming together as the plan that the
residents could agree on as an acceptable solution.
Warren said Ward 8 is on top of the ridge line and does not have to worry about the
water itself, but will have to worry about paying to fix this problem because they would
be paying their share just like anyone else. He said he did not see how $1.7 million
could be spent to save 13 homes and that he would much rather spend $3 million to
save 57 homes.
Beller asked if these alternatives are guaranteed to work. He said a group talked about
water retention this afternoon, and if this structure is built, the water would have to be
dumped on someone and that he did not know who that would be. Beller said the
upstream detention ponds may solve the problem. He said he had gone down 51st
Street and Liberty and drove through deep water, which meant it was not coming from
the north but it was coming from the west. Beller said the Council cannot fix anything
this evening, and no guarantee can be provided that any of these programs would be a
solution, so he felt the detention structure should be built before proceeding further and
see the result of that effort.
Shanklin said the 1999 CIP will be presented to the public when a determination is made
on the Citys water system. He said the south plant produced 10 mgd and may no longer
be able to treat that water. Shanklin said if that capacity is replaced by a southeast
plant, the cost may be $10 million, along with another $10 million for the lines to get it
back into town to replace what was lost. He said the north plant could possibly be
expanded to 35 mgd and we treated that amount almost daily last summer. Shanklin
said the 1999 CIP may all be tied up for the water, not even counting replacing all of the
lines that have had breaks in them during this past year, or for anything else. He said
Lawton is at 70 mils, which is the lowest in the State, and no one wants to compare
Lawton to Norman or Edmond, but Edmond is at 128 mils, although many Lawton
residents would have difficulty affording more. Shanklin said we are at that crossroad
and at that dilemma but that he did not know if there would be any money available.
Williams asked if it would take a year to develop plans and specifications to correct this
problem from the time a Council decision is made. Lilly said after the feasibility study is
approved, it would be nine months to do the plans. Williams asked if Council selected an
option tonight, would the feasibility study come back to the Council after it was
developed for the next step in the project. Lilly said they would want to submit a
feasibility study using the plan the community would support and the plan would need to
be approved by the Corps higher authority, and if that is approved, the Corps would be
funded for the plans, and following that, at that point, they would request construction
approval from headquarters, then request the City to enter into a project agreement,
then go through real estate acquisition and construction. Williams asked if the City had a
financial obligation before that point. Lilly said the Citys share is 50% of the feasibility
study and after the first $100,000, the remaining is a 50-50% cost share.
Williams said he could not see doing the project half way and that there was merit to
Bellers comments because the B-1 pond might solve the problem. He said he would
rather wait to see if the B-1 would do that.
Mayor Powell asked if there is a time table with the Corps in regard to being able to wait
and see if the B-1 project works well enough to not require the additional work. Lilly said
if Council selected the no action plan, the Corps would need to stop the feasibility study,
and it could possibly pick back up in the future, but if there is a significant delay, they
would need to do a final accounting and start over again. Mayor Powell said they were
wondering if the B-1 project would be enough. Lilly said that was addressed in their
calculations. Leach said the flood plain that was shown was considering that the B-1
project was in place, and that they could not guarantee the exact figures on the project
but they could guarantee a reduction in flooding.
Purcell said all of the plans assume the B-1 project is built, which is a $1.7 million cost.
He said on Plan Eight, we go from 52 homes to five in the 10 year flood plain, which is
fairly significant, but we only drop about 12 homes on the 100 year flood plain. Purcell
asked when the last 100 year flood that impacted on Meadowbrook occurred. Ihler said
he was not aware of a time on that particular watershed, although there had been two
on the East Cache Creek basin in the last 15 years. Purcell said all of the flooding
problems that have occurred in that area are based on the 10 year flood, or something
in between, so if Plan Eight is done, we take 47 homes out of the flood area that anyone
has experienced for quite some time. He said Plan Eight was agreed to by 33 people at
one point in time, and under that, 47 of the homes that have been flooding in less than
10 year floods are assisted, although it only reduces the 100 year flood homes by 12
homes.
Shanklin asked if the City had spent about $400,000 on this feasibility study. Ihler said
$150,000.
Haywood asked for Ihlers recommendation. Ihler said from a purely engineering
standpoint, without the emotion for homes flooding or trees being removed, through the
process of elimination looking at the cost and benefit of each alternative, he would not
consider the no action plan or Plan Nine as being cost effective, which leaves the other
three alternatives. Ihler said when you look at 45 homes remaining in the flood plain on
Plan Eight for a cost of $1.7 million, where for only $400,000 more you can go to Plan
Four, from a staff standpoint, Plan Four seems to be the one that is most cost effective
and makes the most sense and has the least effect on the golf course and removes the
most homes from the flood plain on a dollar cost basis. Ihler said from an engineering
standpoint, Plan Four seems to be the most cost effective and it would be
recommended.
Beller asked if the 7-1/2 foot elevation drop is 300 feet into the golf course property.
Leach said 7-1/2 feet is from the beginning of Meadowbrook channel more toward the
main channel. Beller asked what happens to the water after it goes through the country
club property and if it is sent down stream faster, could there be a worse problem. Leach
said there is a very short transition zone; there would be the same volume of water
going down the stream and rip rap would be used in a small area where the velocity
would be higher. Leach said once the water is out of the channel, it will go where it has
always gone.
Mayor Powell asked if the City had the money to fund this project. Baker said no, we
have $3 million earmarked and $1.5 of that is obligated to the B-1 project so there would
be a shortfall, although it would not be extreme.
Williams asked the Corps if the B-1 project was not factored into the flood calculations,
would there be a significant difference. Leach said they looked at it with B-1 and without
it, and if B-1 is not built, the existing 100 year flood would be one foot deeper and as you
go further upstream, it has a greater effect. Leach said you will still have flood damage
below B-1 that you will not have if you do build it so it depends on where you want to
realize your benefits.
Purcell asked the Corps representatives which plan they felt was best from a cost
benefit ratio from their perspective. Lilly said Plans Four and Eight probably have the
greatest benefit.
MOVED by Sadler, to select Plan Eight for this project.
Sadler said while we still have homes in the 100 year flood plain as a result of this plan,
he could not see that everyone would be able to just stop buying flood insurance even if
they got to zero because there is still a potential in being that close to the creek. He said
going from 52 homes to five homes is a significant impact. Sadler said we do not have
the money to do Plan Six and they had to fight long and hard to get the $3 million for the
B-1 project and this one, and it would be difficult enough to do this. He said he felt
funding could be located for Plan Eight and that a major clean up is needed in the
middle section and not just leave it untouched.
Warren asked what the effect on Meadowbrook would be if we did not do B-1 and we
did Plan Six. Leach said for Plans Four, Six and Eight, leaving B-1 out, we would build
the channel five feet wider for the same effect and it is not much of a cost difference.
Sadler said most of the homes that have difficulty getting ambulance service due to
flooding would be removed under this plan. The audience disagreed and Sadler said he
would withdraw that comment if that is not the case. Sadler said Plan Eight calls for
work north and south of the middle section, keeps the massive trees that are so
important to a lot of citizens, and all of the people who signed the petition and attended
the workshop at the Library supported Plan Eight. He said he supported leaving the
trees in place in that area.
SECOND by Smith to Sadlers motion.
Beller asked if funding is available for this option. Baker said it would be real close and
probably could be found in the current CIP. Beller asked if this had to be done tonight
and if Council was prepared to make this decision. Shanklin said until the funds could be
identified and the CIP prepared to send to the voters, he felt action should not be taken.
SUBSTITUTE MOTION by Shanklin, that when we present the CIP and have public
input, to consider it then and table it until that time.
Purcell said he would not support one cent coming from the next CIP to do this; there
are funds in the 1995 CIP and $3 million is already earmarked. He said the funds can be
found from 1995 CIP and that he would go on record as not supporting any money from
the next CIP for this project. Shanklin asked why. Purcell said there are problems with
sewer, water and water distribution. Shanklin said you would not get their help unless
you give a little bit to everybody and Purcell said they are getting $3 million plus.
Baker said we do have approximately $1.5 million to go toward this project. If the cost is
$1.7 million, there is a $200,000 shortage. He said the CIP he was referring to was the
1995 CIP, and not the proposed CIP.
Substitute Motion by Shanklin was withdrawn.
Beller asked the cost of the improvements to the country club. Ihler said the design is
not done so there is not a cost breakdown; there is a rough cost estimate in each plan to
take care of that. Beller asked if the $1.7 million includes all the costs associated with
the country club improvements, renovation, replacement, tee boxes, irrigation, and all of
it, assuming they would be agreeable to the plan. Ihler said each cost estimate included
the work that needed to be done for each plan, to include the golf course.
Ihler said we have spent $150,000 on the feasibility study and that was from the $1.5
million, so we actually have $1.35 million remaining, and about $350,000 would be
needed if it costs $1.7 million.
SUBSTITUTE MOTION by Warren, SECOND by Williams, to stop the B-1 Project and
apply all those funds remaining to Plan Six with the modification that would be needed to
keep the levels at the same place as the plan shows now, with the widening of the extra
five feet.
Warren said in lieu of building B-1, they would widen the channel an additional five feet
to take up the difference. He said that would not change the flooding north of
Meadowbrook, but that was not what was set out to fix to begin with. Warren said the
purpose was to stop the flooding in Meadowbrook, and this is a way to get it
accomplished.
Williams said if the sole purpose is to alleviate flooding in Meadowbrook, the B-1 does
not accomplish that, and the cost for B-1 is $1.7 million. He said plans and specifications
are nearing completion, although there should be a good amount of funds left over that
could be used for channel work in Plan Six.
Sadler said he thought abandoning the B-1 reservoir would be a big mistake because
the land has been purchased and the plans are underway. He said he thought B-1
would be beneficial and should be pursued.
Purcell said he agreed with Sadler and felt the decision on B-1 should not be changed.
He said he understood B-1 would help Meadowbrook and the City is a long way down
the road toward getting that done and others may come forward with flooding problems
that could have been helped by B-1.
Haywood asked Ihler for comment about the B-1 detention. Warren said it was not his
intent to sell the land where the B-1 would be located and that B-1 is needed, but it may
not have to be done right now because both projects cannot be funded at the same
time, B-1 and Plan Six, but Plan Six can be done and then proceed with B-1 later on
because it does not solve this problem at this time.
Ihler said all of the numbers provided in the Corps study, including the numbers shown
on the homes, would be different if B-1 is not done. Warren asked if that would be true
even with the five foot wider channel. Ihler said there had not been a close study about
doing away with the detention pond and the Triad study on B-1 showed a flow reduction
of 20-25% through that area. Ihler said staff recommendation is to do both projects, and
he understood there was a problem with funding, but we are very close to proceeding
with B-1 and it could be in place by the spring rains and provide benefit.
VOTE ON SUBSTITUTE MOTION: AYE: Williams, Warren. NAY: Sadler, Purcell,
Shanklin, Beller, Haywood, Smith. SUBSTITUTE MOTION FAILED.
VOTE ON ORIGINAL MOTION: AYE: Sadler, Purcell, Shanklin, Beller, Haywood, Smith,
Williams. NAY: Warren. MOTION CARRIED.
There was no further business to consider and the meeting adjourned at 7:40 p.m. upon
motion, second and roll call vote.