Month 1998-8 August
Meeting of 1998-8-31 Special Meeting
MINUTES
SPECIAL CALLED MEETING
LAWTON CITY COUNCIL
AUGUST 31, 1998 - 5:30 P.M.
WAYNE GILLEY CITY HALL COUNCIL CHAMBER
Cecil E. Powell, Mayor, Also
Present:
Presiding Bill
Baker, Acting City Manager
John
Vincent, City Attorney
Brenda
Smith, City Clerk
The meeting was called to order at 5:30 p.m. by Mayor Powell. Notice of meeting and
agenda were posted on the City Hall notice board as required by State law.
ROLL CALL
PRESENT: G. Wayne Smith, Ward One
Richard Williams, Ward Two
Jeff Sadler, Ward Three
John Purcell, Ward Four
Robert Shanklin, Ward Five
Charles Beller, Ward Six
Stanley Haywood, Ward Seven
Randy Warren, Ward Eight
ABSENT: None.
Addendum Item: Consider authorizing submission of a revised application for a
Department of Justice Grant, sign the necessary grant application forms, and authorize
the use of City Council Contingency Funds for any required match. Exhibits: None.
MOVED by Shanklin, SECOND by Purcell, for approval of the item. AYE: Warren,
Smith, Williams, Sadler, Purcell, Shanklin, Beller, Haywood. NAY: None. MOTION
CARRIED.
BUSINESS ITEMS:
1. Consideration of funding sources for capital improvement projects and capital
outlay
of the City.
Baker said at the last Council meeting, several projects were discussed for a total of $54
million. Baker asked Ihler to develop three packages for Council consideration, and
those were distributed, with costs of $60, $70 and $80 million over. The projects
discussed from the last meeting are those which staff considers priority projects that
must be accomplished during the next seven years; a package was developed totaling
$60 million with those projects and two important drainage projects to bring it to $60
million; the $70 million package includes the projects from the $60 million package and
added some water line replacements and major arterial street improvements for the $70
million; the $80 million package includes the $70 million package and adds more street
work, the fire station, park improvements, dam improvements, and major arterial street
improvements for the $80 million. The Finance Director was asked to look at each
package and make recommendations for funding each package.
Mayor Powell said some of the items from a previous list were reviewed by staff and
deleted because that should come under funding other than CIP. Ihler said those
projects were the container services for Republic Paperboard Company and installing a
plant chlorine dioxide system to address the turbidity due to the rule EPA is publishing,
but the majority of that cost is for chemicals and after discussion with Baker it was felt
those costs should be put into an annual budgetary type position versus capital
improvements, but it will need to be in the future budget.
Jerry Ihler, Public Works/Engineering Director, said the $60 million list contains the first
phase of the sewer rehab project. It assumes that the $600,000 from the appropriated
Douglas Avenue Project would be available for year two of the sewer rehab. Seven year
program estimate is $15.2 million and additional funds are needed for the initial year
because of the equipment purchases. Second project shown to begin construction in
July 1999 is a maintenance building at the landfill; 100 x 60 ft. existing building is in a
location that will be excavated for cells two and three.
Mayor Powell asked the proposed location of the new building. Ihler said they looked at
going to the north but there were problems with putting it on existing landfilled areas, so
it may be placed across from the existing pit and county line road on the Silk property
where the City has purchased 420 acres.
Shanklin said he felt $50 a square foot for the landfill building was out of line. Ihler said
$50 a square foot was used for the estimate and it would include some parking area.
Shanklin said he did not think the City should be telling the taxpayers to spend $50 a
square foot for a metal building comparable to the existing building, and the estimates
should be as close as possible because they would not be able to do everything and
that the members all had to be in agreement to be able to have a tax pass. Mayor
Powell said the newspaper should be in agreement, as well as all the council members,
to pass a tax.
Ihler said the third item is to expand and rehabilitate potable water pump station one
which serves the west high industrial zone, Goodyear, Republic Paper, Bar S and Pecan
Valley. Once Republic begins receiving 1.5 million gallons, along with Bar S and any
future expansion, that will maximize what can be delivered by pump station one to the
industrial area. Recommendation is to upgrade the pump station to be able to deliver a
greater volume to the industrial park. Shanklin asked if staff had contacted Hutchinson,
KS to see how much their Republic plant is using and Ihler said no. Ihler said several
construction meetings were held with paper company representatives and they feel very
comfortable that they will be using the 1.5 million.
Ihler said the next project is the upgrade of the plant chemical disinfection and EPA may
establish a law in June 1999, and we would like to be in operation by June 2000. It is a
Clean Air Act compliance issue requiring any facility that contains one ton chlorine
cylinders, which we use at the water and wastewater plants, we must have an air tight
facility that should there be a chlorine leak that it would all be held within that facility.
Shanklin asked if you could go to a 1,000 lb. cylinder. Ihler said he thought it would
apply to any chlorine container. Ronnie Graves said he did not know if chlorine cylinders
were available in other sizes but smaller containers would result in changing them
frequently. Shanklin said $2.5 million is a lot of money. Graves said he could check to
see if an alternative approach could be used. Beller said the past election was for the
$62 million infrastructure and felt there would be strong opposition to including a lot of
other items, such as $450,000 for the pump when they asked staff if we could handle
the volume for Republic and they said yes, and asked if he was wrong. Ihler said staff
indicated the pumps would handle the 1.5 million and this pump is for any additional
growth that would occur at the industrial park.
Warren said the first page contains items that must be done by the end of seven years,
with the exception of the maintenance building. Ihler said they could check on the
chlorine cylinders. Beller said he could disagree that all of the items had to be done
because one statement is the volume of waste to the landfill has increased due to the
volume of waste from outside city sources, so if we discontinue to take the waste from
outside city sources, they could save $4.5 million. Warren said the items are not
required if you tread water for a while but that approach got the City in the shape it is in
now.
Purcell said it is the same problem with actions not having been taken in the past and
the result is the $62 million sewer problem today. These items should be addressed so
similar problems are not experienced in another five or ten years and it should be
emphasized to the media that this is not a wish list but is mandatory. Problems are
caused when the media puts out bad information, and this is not a wish list, although
some of the items in the $80 million may be, but this is not.
Williams said we do not want future councils to be in this shape and have to go back out
again and ask the voters for more money. He said the needs in the next five years
should be identified and addressed, and everyone would have to be in agreement
before going to the voters and the items are not a wish list at all.
Shanklin said we have not factored in that if 40% of the waste stream is paper, 90% of it
will be recycled by the paper plant, and that fact was not addressed. Ihler said there are
three cells and at the time the report was prepared, the landfill was receiving about
100,000 tons a year and five years of life was estimated for each cell; the landfill
received 122,000 tons last fiscal year which takes away one year from each cell. The
existing cell has been in use for approximately four months and continuing at the
120,000 ton rate, it will take a year to construct and another six months or year to design
and you must be ready to move into the cell. The way the sequencing has been set up
with DEQ, it should begin to be addressed now.
Shanklin said if the $4.5 million was put into the plant the firm had in Southwest
Arkansas, neither of the cells would be filled in 150 years. Ihler said it was an $8 million
capital investment. Shanklin said it was closer to $4.5 million and the reduction in waste
stream from paper recycling should be factored in. Ihler said the paper mill comes on
line in November 1999. Further discussion was held regarding the waste recycling
operation in SW Arkansas and the fact that no other cities currently use that method
fully, although it could be a pilot project.
Ihler said the next item is to replace the existing north water plant filter media, which is
mono media and can be replaced with dual or tri media, which are both capacity and
compliance issues with turbidity; the north plant at Medicine Park could have an
increase in capacity from 25 mgd to 30 mgd and assist in meeting the upcoming
turbidity requirement in 2002. EPA also indicated that every filter must be individually
monitored and recorded for turbidity, and Lawton currently monitors only the effluent that
comes off of all the filters as the combined product; estimated cost for that improvement
is $500,000.
Ihler said the next item is to construct a Southeast Water Treatment Plant. The Medicine
Park plant has a rated capacity of 25 mgd at the north section and 10 mgd at the south
section. With the new Safe Drinking Water requirements neither plant could meet the
standards without modification. Modification can be made to the north plant, but not to
the south plant. Depth of the filter beds in the south plant are such that you cannot add
filter media and meet the necessary hydraulic flow, also the plant is 67 years old and
useful life is usually 50 years. Recommendation is to replace that 10 mgd capacity with
a 20 mgd module in Southeast Lawton which would allow for better use of the water
rights, specifically from Lake Ellsworth, and it would probably cause Lake Ellsworth to
become the primary water source. Water would gravity flow from Lake Ellsworth to the
Southeast plant but it would have to be pumped from that plant back into the Citys
system and cost is presumed to be similar to those from pumping from Ellsworth to
Lawtonka. Lake Waurika water could be used as a secondary source for the Southeast
Plant, and water would be pumped from Waurika to the Southeast Plant then pumped
into the City system.
Shanklin said it costs $1 million to run the Medicine Park plant and it will cost another
million to run another one off the top of the budget, and asked Ihler if that is correct.
Graves said the water plant budget is $1.8 million but over $1 million of that is for the
assessment for Waurika. Ihler said the $1 million operational cost is a fair estimate.
Purcell said for purposes of the media, the projects for $54 million are mandatory and
not a wish list and that word should get out to everyone and not be lost in the
translation.
Shanklin said the current contractor at the wastewater treatment plant built a plant at
Lewisville, TX for 85 cents a gallon, and that city would face the same regulations. Ihler
said they would build the most cost effective plant possible, the figure shown was
recommended by design engineers and it was $1.50.
Baker said another reason the Southeast Plant is shown as a high priority is because it
is critical for economic development. A major industry will not look at Lawton without
excess treatment capacity and most large industries use volumes of water. Shanklin
asked if all industries are large users and Baker said no, but those that do use large
volumes of water would not seriously look at Lawton if that water cannot be provided
daily at a certain pressure and volume.
Beller said he did not see the people in general demanding economic development. He
said if economic development funding is tied to this issue it will fail. Beller said it is a
good thing to pursue but would not assist in selling an infrastructure tax issue to the
voters. Williams said the residents are concerned about jobs, the future of the
community, the tax base and Fort Sill as far as the downsizing of the military, and if the
community is to grow, it must take a giant step up. Williams said some of the items are
growing pains and some are in essence unfunded mandates. Purcell said he agreed the
average citizen would not support economic development, but if it is shown as getting
more jobs for their kids and grandkids, they would care about it and that is what council
refers to as economic development, so it is how it is presented.
Ihler said the south section of the water plant will not be able to meet the Safe Water
Drinking Act mandates, therefore, Lawton would be unable to treat the capacity it
currently treats at the Medicine Park plant. For the entire month of July, the average was
33 mgd and if the capacity of the south portion is taken away, there is only 25 mgd
available so Lawton would have been short 8 mgd. The new plant would replace some
of the capacity to keep up with the current requirements, plus provide some growth for
economic development. Mayor Powell said the capacity will be required for existing
citizens and use and that is an important point.
Ihler said page two shows the $60 million CIP package and contains the projects just
reviewed for $54.2 million with two additional projects. One of those was the Middle
Branch of Wolf Creek drainage improvement and funds were identified in the 1995 CIP
to start on that project. A feasibility study is being done with the Corps of Engineers and
when completed, it will come to Council, and depending on the benefit/cost ratio with the
Corps, the Corps may participate in some improvements. Ihler said it is estimated that
as much as an additional $2.5 million may be needed for that entire program, not
knowing yet what the cost will be for the channel work. There is a fairly good idea of the
cost of the work for the detention reservoir being considered just east of 67th Street and
south of Rogers Lane, it will be about $1.5 million which has been earmarked already for
that project, and $1.5 million has been earmarked for the Corps project. Because of the
large amount of right of way that is necessary to be purchased for the Corps project on
the Middle Branch, it may be a 50-50 cost share project with the Corps. The alternatives
the Corps is looking at, the one they support at this time, is in the neighborhood of $4 to
5 million although the design work has not been done and this is part of the feasibility
study.
Sadler asked if we were currently proceeding with the detention pond at 67th Street.
Ihler said the final design phase is in progress for the detention pond and should be
ready for Council around the end of the year for approval of plans and specifications and
to authorize advertising for bids for construction. Sadler asked if that can be done with
the $3 million. Ihler said yes.
Shanklin asked if Ihler would rather have the detention pond than do the Wolf Creek
drainage, and asked what the Wolf Creek drainage would do to the people who have
been flooded in the past. Ihler said the Corps has provided, in the feasibility study, that
with a 100-year storm frequency on the Middle Branch of Wolf Creek, somewhere in the
neighborhood of 60-65 homes would be flooded. The Corps design shows an 80-year
storm could be carried within the channel, bank to bank; that is without the construction
of the detention pond, and including the detention pond, it would be able to carry the
100-year storm.
Shanklin said the City has refused to go to the State to get rid of the ox bow at Cameron
University and the dam between Gore and Lee; at 44th and Gore at five feet depth of
water you have 500 feet going south and when it gets to the bridge at 38th and Lee, at
five feet high you have 275 feet of space. He said logic says it raises and backs up to
where it began. Ihler said it would raise and spread out, and spread first. Ihler said when
the numbers were reviewed three years ago, when the report was done for south of
Gore, it was that the entity receiving the spread of the water would be Cameron
University.
Sadler said most of the residents would like the flooding problem in Meadowbrook
attacked from both ends, by going through the country club with a channel of grassy
slopes, not a big, ugly concrete channel necessarily, but to get the water out faster and
to use the pond to slow up the water coming in. He said residents did not favor a large
concrete structure and ripping out all the trees. Ihler said the channel being considered,
and it is in the feasibility study phase, is a 60-foot bottom width grass lined channel with
a 120-foot width at the top. Ihler said some of the residents do not want the channel to
go through their back areas because it would require removal of trees and some of the
residents want it to be constructed to relieve the flooding. Ihler said that would be a
decision the Council would make.
Beller asked if there was a concern about the wildlife in that area also. Ihler said part of
the process the Corps must go through is an environmental assessment, which would
address the issues from the standpoint of species and habitat; a comment period is
established for those in the area to comment, and that is then evaluated. The Corps
must feel comfortable that they are not causing any trouble or damaging the habitat that
could not be mitigated, and an example of mitigation is where trees must be removed
they could possibly plant new trees in a nearby area. Beller said he understood the
Terrills had a bird sanctuary map of that area. Ihler said he did not know it was a bird
sanctuary, although there was concern that it was considered a wetlands area, and all of
those issues must be addressed by the Corps of Engineers, which could suggest
mitigation or that because of the opposition, they not move forward. Beller said to put a
$5 million package together for 65 homes, not knowing how many would receive relief,
was not good and the only guarantee was to buy those homes, which seemed to be
more logical. Beller said things like this being included in the package could be
detrimental, and the citizens need solid information on what the tax will be spent on.
Williams said something has to be done with Wolf Creek, either buy the homes, spend
money, or do nothing and have citizens come forward saying their homes have flooded
requesting relief. He said it benefits a specific area, but that is also the case with certain
parks, streets, or water lines.
Ihler said the next project in the $60 million package was a drainage improvement which
had been in the 1995 CIP for 34th Street south of Cache Road in Greer Addition. The
street is not passable even after a very small rainfall and it is a route used for hospital
access. The drainage is a concrete box that starts near Cache Road and winds through
Greer Addition behind Tomlinson Junior High tying into Squaw Creek. Shanklin said it
had been prioritized in the top five for the last 13 years. Purcell said this is both a street
and drainage and appears to be more important than Wolf Creek because it would
benefit many more people.
Ihler said the next page goes into the $70 million package, which includes the $60
million package as well as $2 million for major and minor water distribution line
replacement City wide and the specific lines were identified in the large package
distributed previously. Mayor Powell asked how those lines were identified. Ihler said
they were identified over the years based on the number of breaks in the areas. Ihler
said the remaining $8 million in that package is for arterial street improvements; three of
the five projects were sent to the Oklahoma Department of Transportation for the
highway bill requesting federal and state funding. If the projects were totally funded with
City money only the first two could be done. Ihler said with highway participation, similar
to Rogers Lane, the City is responsible for engineering, right of way and utility relocation
costs 100% and it is assumed that those costs will be about 25% of the entire project,
so the City would be responsible for 25% of the entire project cost. Construction is
usually an 80-20 split,
with 80% being federally funded and 20% can either come from the local government or
the state, and the State is putting in 20% for the local agency on Rogers Lane; if the
state does not fund the 20% the City will need that funding for the match.
Williams asked if all of the projects shown would qualify for matching funds from federal
or state. Ihler said the projects listed are all of the TIP program and would qualify.
Purcell said the projects come to $22 million and asked if the City had $8 million for
match that it could get $22 million done in construction. Ihler said the $8 million was the
number to fill out for the $70 million package. Purcell said $5.69 million is shown at the
bottom and asked if that was assuming the state would come in with funding. Ihler said
if the state will pay the 20% local match, the City would need $5.69 million; if the state
does not, the City would need $9.1 million. Baker said Lawton should make an effort to
take advantage of the state and federal funding available and that matching funds are
needed to do that. Shanklin said it would still be a priority question in the various
projects in the overall program.
Ihler said the last page shows the $80 million package, which includes the $70 million
package as well as NW 31st Street Reconstruction to include a drainage improvement
from north of Gore to NW 25th Street, on the east side of Memorial Hospital and is
much like the 34th Street project. $2 million is included for minor street repairs
throughout the City; priority list is in the large package. $650,000 is included for
relocation of Fire Station #5. Lake Ellsworth and Lawtonka dam improvements at an
estimated cost of $1.125 million. $1 million is included for parks improvements, to
include Eastside, McMahon, Grand View and City-wide parks. Major arterial street
improvements are shown and it would be the same case on the matching funds.
Shanklin asked how many of these projects would be done in the CIP starting in 2000.
Ihler said the only project identified in the existing, ongoing 1995 CIP was the Wolf
Creek project. Shanklin asked if we were trying to generate an additional $10 million
new money in addition to the CIP, and explained that the funding estimated to be
received from a five year sales tax was not sufficient to fund the projects listed. Baker
said three funding packages were developed by the Finance Director to match the
programs at the rates of 1%, 1.25% and 1.50% sales tax, as well as utility rate
increases. Shanklin said if the one cent sales tax generates $40 million, there would be
a need for an additional $20 million spread out over the five-year period. Purcell said
that would be for the $60 million package and Shanklin agreed.
Steve Livingston, Finance Director, said information was distributed showing 1%, 1.25%
and 1.50% sales tax for the period January 1, 2000 through December 31, 2004. He
said Shanklins questions are addressed on the next page where the $60, 70 and 80
million programs are shown because none of the sales tax percentages shown will
generate sufficient funding for the estimated project amounts for even the $60 million
program. Utilities are shown as the additional revenue source because so much of the
costs are tied up with one of the utilities, water, sewer or refuse, so the utility increase is
shown. He said a 1% sales tax for five years to fund the $60 million program would
require $8.50 per month on the utility rates; 1.25% sales tax would require $5 per month
on the utility rates; 1.50% sales tax would require $1.50 per month on the utility rates.
The $70 million program shows the 1% sales tax would require $12.50 per month on
utility rates; 1.25% would require $9 per month, and 1.50% would require $5.25 per
month. The $80 million program shows the 1% sales tax would require $16 per month
on utility rates; 1.25% would require $12.50 per month, and 1.50% would require $9 per
month.
Livingston said one question was what would be the utility rate increase now that we
have applied two years of the CIP to phase one of the sewer rehab, that number comes
to $5.70 and is included for information purposes. It does not address the overall CIP
$60, 70 or $80 million.
Purcell said the $60 million program shows 1% sales tax and $8.50 utility increase; if the
1% sales tax was defeated, would the utility increase be in the area of $26 or $27 per
month to make up the $60 million. Livingston said he did not look at that, and there
would be a question of whether all of those items could be placed on the utility bills, but
at least those amounts would be required to fund the entire program.
Vincent said Williams asked a question last week regarding whether street
improvements could be placed on the utility bills. He said his office had researched that
and the drainage projects could be on the utility bill, but for items such as the major
arterial street improvements, if the intent is to raise revenue to fund non-utility items, it
must go to a vote of the people. Street improvements can be charged through special
assessment districts or other situations but not on the utility bill. Shanklin asked how
funds are transferred from the enterprise fund and placed in the general operating
budget in the amount of $8 million, and is then used to pay police, fire, streets,
everything. Vincent said you are allowed to have excess funds through the utility, but the
question was whether funds could be earmarked on the utility bills as a street
improvement and you cannot because it is a revenue raising measure. Vincent said if a
certain amount is budgeted for a project and it comes in under the amount, the excess
can be transferred to the general fund, but you cannot do it strictly as a revenue raising
measure without going to a vote of the people.
Mayor Powell said one thing to think about would be to take the $30 million water
treatment plant off and deduct that from each of the packages brought forward, which
would leave a $30, $40 and $50 million set of CIP packages, and fund the treatment
plant with a utility increase. Purcell asked if a decision was made to increase the utility
bill $25 a month, can that be done. Vincent said in general terms, yes, as long as it is
reasonable in making the association with the utility and not inflated only to be able to
pay for other items, such as street repairs.
Shanklin asked how critical it is to Council that this be presented on the November 3
ballot. Purcell said he felt it was absolutely critical. Shanklin asked if it could not wait
until January or February. Purcell said it has already been delayed six months and there
will be a problem with DEQ if there are further delays; there may also be another sales
tax issue on the ballot in November and that could be discussed Tuesday. Shanklin
asked if Council had to agree on all of this be Wednesday. Williams said he thought it
should be done in a timely manner, although the proposed tax would not take effect until
the year 2000, and/or a utility increase that would not take effect until January 1999, but
a decision is needed. Beller said Purcell suggested we were losing money, but if it does
not start until January 2000, what is being lost. Purcell said the other part would have to
kick in on the utility increase, whatever it turns out to be, in January 1999.
Haywood said the county may come up with a question on the jail and the school
system may come up with something for a junior high school. He asked if it was felt that
the Citys issue would pass. Purcell said he hoped there could be discussion with the
county tomorrow night, and some room may be left for that; the Citys extension would
start January 2000 and if it is 1% it leaves room for the county for economic
development or a jail, and the countys would almost be over before the Citys would go
into effect. Purcell said the school system would not make the November 3 ballot and
that he did not know when it would come up again, but it is also something to consider.
Williams said the school system received revenue from property sales recently and may
need only a small ad valorem levy.
Keith McDonald, Leo Oppenheim Company, said he did a capital funding report for
Lawton in 1994 for the 1995 CIP, and the report was updated last October in looking at
the SRF for wastewater treatment improvement funding. He distributed information
regarding comparison of water and sewer rates in cities in Oklahoma. The sources of
revenue are utilities, sales tax and ad valorem. If utilities are raised $8.50 per month,
Lawton may be approaching the mid range but would still not be in the median of the
rates charged in other cities in the state. He said the citizens should appreciate the rates
having been maintained at the lower level, but at the same time, the water and
wastewater systems have suffered since those improvements have not been made.
McDonald said information was distributed comparing ad valorem rates of cities in the
state showing schools, counties, etc. and a total column. There is flexibility in this area
also since the ad valorem rates are lower than those in other counties. Many cities
request ad valorem taxes for non-revenue producing items such as fire stations,
drainage, parks, etc. and use the water and sewer rates to pay for the water and sewer
services.
McDonald said he was asked to report on pay-as-you-go versus debt financing, and that
was also done in October 1997. He said it was determined previously that pay-as-you-go was not as efficient
as the debt through OWRB. McDonald said one handout shows
a $1 million increment and the OWRB program through SRF allows for borrowing 40%
of the money at zero percent interest rate; 60% of the money is at market interest rates.
If the City got $1 million up-front to be able to award the contracts, and spent someone
elses money at a zero percent interest rate, they obviously have the ability to invest
their money at 5-6%, so would be arbitraging by using that money. McDonald said he
composed a debt schedule of what would be paid if they went to the OWRB and
borrowed the same $1 million; if they invested that $1 million at 5%, by the time the
payment is due to the OWRB, they would have generated $50,000 in interest income,
and after paying the debt service for that year would have $869,000 which would be
invested during that period at 5%, and by the end of the period there would be funding
remaining. McDonald said in certain situations it is beneficial to use someone elses
money and invest their own money.
Shanklin asked how much the City can borrow and McDonald said Lawton is on the
priority list for $14 million. Shanklin pointed out that some of the cities shown on the
comparison sheet have per capita income that exceeds that of Lawtons population, and
at one time Lawtons was below Arkansas, which was ranked 48th nationally in per
capita income.
Williams asked if a request had been submitted to OWRB for Lawton to receive $14
million. McDonald explained the programs available through OWRB and said Lawton is
on a priority list but an application would be required; the purpose of the program is to
allow cities to make water and wastewater improvements at a lesser cost. Williams
asked if there was a way to get more than the $14 million. McDonald said the entire
program cost was shown at $62 million so OWRB anticipated Lawton would attempt to
get on the list for a larger amount, and that Tulsa uses as much money as it can get
from the program.
Purcell asked if Lawton could take the $14 million for the sewer portion, and another
amount from OWRBs water program to use for the water treatment plant. McDonald
said yes, the program was designed for such uses and the seed money came from the
federal government in an attempt to let the states design programs to benefit their
communities. Williams said it seemed Lawton should take advantage of the programs
available.
Mayor Powell said mass transit in the amount of $1.3 million was not included on the
lists but it should be considered in the discussion.
Beller suggested members be allowed to think about these overnight. He said there was
nothing shown that was not necessary, and some are mandated, but he was of the
opinion that a definite program would be needed before going to the public requesting
tax funding with a definite period of time.
Mayor Powell said Lawton has 1.25% sales tax and it will expire December 31, 1999.
Beller said that would bring the total sales tax down to 6.5%. Powell said he asked for
the figures on the 1.5% sales tax for information and it would make it easier on a utility
increase.
Williams said there is a tremendous match available from the federal government for the
mass transit and even though $1.3 million is a lot of money, much of it would be funded
through transportation funds from the federal government.
Mayor Powell said he hoped everyone would go to the fire station on 53rd Street, the
beds have bricks under them to level them, so it has a problem.
Baker asked if there was guidance to staff and there was none at this time.
2. Consider adopting an ordinance assessing and levying an excise tax beginning
January 1, 2000, for a specified period to be used for capital improvement projects and
capital outlay of the City, and submitting the ordinance to a vote of the electorate,
adopting a resolution setting the date for a special election and establishing the
questions to be placed on the ballot.
This item was not considered separately although it was generally discussed as shown
above.
COMMENTS.
Smith congratulated Vincent on the birth of his first grandchild.
There was no further business and the meeting adjourned at 7:15 p.m. upon motion,
second and roll call vote.